Study for the ITIL 4 Foundation Exam with comprehensive multiple choice questions and flashcards. Each question offers hints and explanations. Ace your exam with confidence!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


The Change Control process includes what key aspect?

  1. Strict enforcement of IT policies

  2. Assessment of risks associated with changes

  3. Direct supervision of IT staff

  4. Product marketing strategies

The correct answer is: Assessment of risks associated with changes

The Change Control process is fundamentally about managing changes in a way that minimizes risk and disruption to services. One of the key aspects of this process is the assessment of risks associated with changes. This involves evaluating potential impacts on existing services, systems, and operations before a change is implemented. By identifying risks, organizations can make informed decisions about whether to proceed with a change, implement additional safeguards, or possibly delay the change until mitigation strategies are in place. Effective risk assessment ensures that all stakeholders understand the potential consequences of a change, allowing for better planning and readiness. This is crucial in maintaining service quality and ensuring that changes contribute positively to the organization rather than introducing new issues. The other choices do not align with the primary focus of the Change Control process. While enforcing IT policies is important in a broader sense, it does not directly pertain to how changes are evaluated and managed. Similarly, direct supervision of IT staff and product marketing strategies are outside the scope of Change Control, as they do not concern the assessment and implementation of changes to IT services or infrastructure. Thus, the emphasis on risk assessment is what distinctly defines a robust Change Control process.